What are the eight points of attention after installing the suspension permanent magnet- RCYD
the email of beltmagnets factory

HomeBlog › What are the eight points of attention after installing the suspension permanent magnet

What are the eight points of attention after installing the suspension permanent magnet

Suspension permanent magnet can be used for material removal in different industries, and can continuously and continuously absorb and release iron. There are many specifications for suspensionpermanent magnets, which are usually installed by professional technicians during installation. After the suspension permanent magnet is installed, it must be carefully checked before use. If it is improperly installed, it will affect the normal operation of the suspension permanent magnet and have a great impact on the iron removal operation. Therefore, after installing the suspension permanent magnet, you should pay attention to the following items:

1. Check the reliability of the connection between the two ends of the suspension permanent magnet suspension device.
2. The suspension height of the suspended permanent magnet is initially determined as the adjustment measurement of height ≤ H. If the installation is inclined, in addition to checking the height ≤ H, the inclination angle α is also detected.
3. Check the safety and reliability of the track limit device of the suspension permanent magnet walking trolley and the stability of the trolley running.
4. After the suspension permanent magnet travels the trolley to reach the limit of the iron and the iron, the center line of the suspension permanent magnet should be aligned with the middle of the belt and the middle of the abandoned iron trolley.
5. If two suspension permanent magnets are installed on a belt, check whether the alternate operation is accurate and in place according to the program control requirements. Is it stable and reliable? The idling operation must be tested at least 10 times per trip, and no trials can be put into operation.
6. After putting into production trial operation, pay more attention to observe the operating status of the host, the ability to suck and reject iron, and the accuracy of the stop position after the limit. Running the program alternately is not confusing.
7. Pay attention to the operation status of the suspension permanent magnet and the ability to absorb and reject iron. It is possible to artificially input the iron of different weights and shapes into the material to be conveyed, and to test the suction and abandonment ability of the main machine. If necessary, the height or inclination should be adjusted (the heavy iron and the excessively sharp iron should not be invested during the test).
8. If there is no problem within 24 hours of continuous trial production operation, it can be put into formal production operation.

Suspended permanent magnet